Copy a Calendar Structure

Follow these steps to crate a new calendar structure from an existing one.

  1. Select Project Data > Calendars in the Navigation Menu. The Manage Calendars tab window displays.
  2. Click the New dropdown in the Ribbon Menu and then click Copy From. A Copy Calendar dialog box displays.
  3. Enter a Name and Description.
  4. Select the calendar structure you want to copy from the Structure From dropdown.
  5. Click Save in the dialog box. The Manage Calendars window updates to display the content of the calendar structure you just created.
  6. Optional. Close the Manage Calendars tab.